- Rough plaster applied in ladies toilets (wall and window) - Andrew
- Inner wings of the stage - second coat applied - Heather
- Chair rail sanded - all around the room -Dan
- Chair rail painted first coat of burgundy - 5 metres Dan, the rest done by Kev G.
- Outside wall pressure washed, more to do, but good progress - Skip
- Window outer sill replaced - rotten wood removed and new tanilised wood used - Pete
- Tape and plaster applied to ceiling repair - Andrew
- Wall in hall - first coat of paint applied to west wall - Jon & Matthew
Sunday 1 March 2009
Sunday morning shines
A 9am Cub route walk by Baggy and Akela saw time for a cuppa and then into the hall for 10:30. Skip, Heather, Jon WM and Kev G pitched up (thanks all). We tacked the following jobs: